November 23rd - 24th, 2017
- Grinded damaged bow fiberglass
- Laminated bow
November 23rd, 2017
- Demounted Cockpit Shower and water pipes
- Mounted new Boom Vang Hydraulic Panel
- Dry fitted Radio in Hydraulic Panel
November 21st,
2017
- Demounted and took watermaker component ETD (Energy Transfer Device) to Malcolm => measured thread 1/4 British Pipe Thread BSPP); dry
fitted connection fittings and hoses (~5’)
- Measured Hose length ... 40’ (39,8’) and took Boom Vang Hydraulic Components to Malcolm => dry fitted hydraulic components (pump,
needle valve, pump lever) and connected components with hoses in to the panel
November 13th,
2017
- Mounted welded portside upper Spreader
- Installed SSB Antenna Insulators in Backstay
- Exchanged Upper Shrouds (incl measuring and swaging)
- Mounted new gWind
- Mounted new Windex
- Pulled Flag halyards
- added stem ball cones to all shrouds ... more contact area
- Tensioned Rigging (shrouds & stays & Rollerfurler)
- turned Foresail Rollerfurler Drum
November 11th,
2017
- Finished assembly Windlass and mounted Windlass with new backing plate in position
November 10th, 2017
At Dons Workshop ...
- welded Spreader crack (material Alu)
- Backing plates Windlass 14 x 8“ D1/4“ water jet cut out Alu 6061
- 4Pc Backing plates Cleats 3 1/2“ x 3“ D1/4“ water jet cut out Alu 6061
- Windlass Baseplate water jet cut out 4 3/8“ x 12 5/8“ D3/8“ Alu
- Engineered Outboarder Hoist
November 8th,
2017
- Demounted Staysail Rollerfurler, exchanged damaged foil, mounted Rollerfurler
- Demounted upper port side Spreader => discovered Crack close to base
November 7th,
2017
- Wired and connected compass light
- Cleaned bottom => not many Barnacles, more slime. Blister on rudder located
November 6th, 2017
- Installed engine diesel injectors
- Engine test run & calibrated engine RPM display
- Mounted the second windgenerator holding rod
November 4th - 5th,
2017
- Installed Main AC Pump and Seastrainer in a new location
- Installed USB and 12V plugins at the Cockpit Chartplotter
November 2nd - 3rd,
2017
- Deinstalled Injectors on the Perkins 4.108 for testing
- Coastal Diesel Injection Service: Dropped off engine injectors for cleaning and nozzle replacement. Tested spray pattern => nok. Decided for nozzle replacement
October 31st - November 3rd, 2017
- Cleaned and derusted all Windlass parts in workshop
- Assembled Windlass
October 30th, 2017
- Taped, sealed and installed new port side (back) window
- Demounted second window on starboard side (front) and removed old sealant
- Bow navigation lights connected with new wires and mounted lights
October 29th, 2017
- Demounted old leaking freshwater foot pump head
- Disassembled and cleaned old freshwater foot pumps (galley and head)
- Mounted cleaned freshwater foot pump (head)